Question: could i have the answer for these two question : c) What is the total cost of the project before and after crashing? Explain the

could i have the answer for these two question :

c) What is the total cost of the project before and after crashing? Explain the costs included in the calculation briefly. (10 points)

d) What is the Max. Crashing time for the overall of the project? Explain briefly (meaning that how many weeks you can perform crashing) (5 points)could i have the answer for these two question :

18 Time Activity A B D Normal 9 12 13 24 21 16 19 26 15 12 Crash 8 10 11 21 20 14 16 23 12 10 Normal 24000 36500 24000 44000 49000 37000 63500 16750 22000 11500 Crash 25000 39500 26000 45500 52000 38000 71000 19000 25000 14500 CPM IS A CEFIJ a) Calculate the Max. Crashing Time and Slope for each activity. (10 points) b) Crash the project (reduce the duration) for 8 weeks. (15 points) c) What is the total cost of the project before and after crashing? Explain the costs included in the calculation briefly. (10 points) d) What is the Max. Crashing time for the overall of the project? Explain briefly (meaning that how many weeks you can perform crashing) (5 points) Q2. Based on the given table below, answer the questions. (20 points) Show all calculation steps in the answers Direct Costs Activiy Slope Normal Crash Max. Crash Time B D E F G CPM is ACEFG MOODS Time 5 6 12 14 8 10 7 Cost ($) 110 160 120 110 200 80 140 Time 3 3 10 11 4 7 5 Cost ($) 170 280 210 200 300 170 240 a) Calculate the Max. crash time and slope (10 points) b) Crash the project for 7 weeks, calculate the total cost before and after crashing (10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!