Question: Based on the given table below, answer the questions. (40 points) Show all calculation steps in the answers Activity Time (weeks) Cost (KD) Max. Crash
Based on the given table below, answer the questions. (40 points)
Show all calculation steps in the answers
| Activity | Time (weeks) | Cost (KD) | Max. Crash | Slope | ||
| Normal | Crash | Normal | Crash | Time |
| |
| A | 11 | 9 | 25000 | 26000 |
|
|
| B | 13 | 11 | 36500 | 39500 |
|
|
| C | 14 | 12 | 24000 | 26000 |
|
|
| D | 25 | 23 | 44000 | 45500 |
|
|
| E | 23 | 21 | 49000 | 52000 |
|
|
| F | 17 | 15 | 37000 | 38500 |
|
|
| G | 20 | 18 | 63500 | 71000 |
|
|
| H | 27 | 24 | 16750 | 19750 |
|
|
| I | 16 | 13 | 22000 | 25000 |
|
|
| J | 13 | 11 | 12500 | 15500 |
|
|
CPM is A D E G H J
a) Calculate the Max. Crashing Time and Slope for each activity. (10 points)
b) Crash the project (reduce the duration) for 7 weeks. (15 points)
c) What is the total cost of the project before and after crashing? Explain the costs included in the calculation briefly. (10 points)
d) What is the Max. Crashing time for the overall of the project? Explain briefly (meaning that how many weeks you can perform crashing) (5 points)