Question: Could you please answer for the above question by give the steps as well. Develop the material requirements plan for component H of the end



Could you please answer for the above question by give the steps as well.
Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and each component except B are one week. The lead time for B is three weeks. Sixty five units of A are needed at the start of week 8 . There are currently 23 units of B and 105 units of E Projected on-hand, and 30 units of H are in production by a supplier and are scheduled to be received by the start of week 2. (Do not leave any empty spaces; input a 0 wherever it is required.) =