Question: Could you work out the network model Save Answer The following table shows the activities needed to complete a project along with precedences and activity

Could you work out the network model Save AnswerCould you work out the network model

Save Answer The following table shows the activities needed to complete a project along with precedences and activity durations. The precedence column (headed Follows) shows which activities must be completed before given activity can begin. Estimates of durations (days) Activity Follows 12 AL -- B -- C -- D A E A B G B, C Optimistic | Most likely Pessimistic 1 2 3 L 2 4 9 2 - 14 L 6 9 A-ON-N- 4 W - Wooco H D 1 1 E, F, G JL B, C 1