Question: Course: Construction Mgmt & Scheduling, CET 4 4 6 0 Homework Assignment 3 ( Due Date: Tuesdav, 1 0 / 2 2 / 2 0

Course: Construction Mgmt & Scheduling, CET4460
Homework Assignment 3(Due Date: Tuesdav,10/22/2024)
The following table shows information related to the major activities of certain project.
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Optimistic Time],[(Week)]],\table[[Most Likely Time],[(Week)]],\table[[Pessimistic Time],[(Week)]]],[A,-cdots-cdots---10,14,,],[B,-cdots,6,10,12],[C,A,5,08,15],[D,B,9,12,6],[E,C,4,6,7],[F,D, E,10,5,20],[G,D,11,14,22],[H,E, F,10,16,20],[I,F, G,16,15,28],[J,H, I,6,20,14]]
a. Determine the probability of completing the project by week 70.
b. Determine the probability of completing the project in more than 70 weeks.
The following table shows information related to the major activities of certain project.
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Optimistic Time],[(Week)]],\table[[Most Likely Time],[(Week)]],\table[[Pessimistic Time],[(Week)]]],[A,-cdotscdots-cdots,6,10,14],[B,-cdots-cdots,5,08,12],[C,A,9,12,15],[D,B,6,6,6],[E,D, E,4,5,7],[F,D,10,14,20],[G,E, F,11,16,22],[H,F, G,10,15,20],[I,H, I,6,20,28],[J,16,10,14,]]
a. Determine the probability of completing the project by week 70.
b. Determine the probability of completing the project in more than 70 weeks.
 Course: Construction Mgmt & Scheduling, CET4460 Homework Assignment 3(Due Date: Tuesdav,10/22/2024)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!