The following table shows information related to the major activities of certain project.
tableActivitytableImmediatePredecessortableOptimistic TimeWeektableMost Likely TimeWeektablePessimistic TimeWeekAcdotscdotsBcdots,CADBECFD EGDHE FIF GJH I,
a Determine the probability of completing the project by week
b Determine the probability of completing the project in more than weeks.
The following table shows information related to the major activities of certain project.
tableActivitytableImmediatePredecessortableOptimistic TimeWeektableMost Likely TimeWeektablePessimistic TimeWeekAcdotscdotscdots,Bcdotscdots,CADBED EFDGE FHF GIH I,J
a Determine the probability of completing the project by week
b Determine the probability of completing the project in more than weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock