Question: Course: System Analysis and Design Code: IT 353 The following project activities have been defined with their required times for completion. Draw a network diagram

Course: System Analysis and Design

Code: IT 353

The following project activities have been defined with their required times for completion.

Draw a network diagram for the activities.

Calculate the early start time and early finish time.

Calculate the late start time and late finish time.

Show the critical path.

Task ID

Task predecessors

Duration (days)

A

-

3

B

A

4

C

A

2

D

B

5

E

C

1

F

C

2

G

D, E

4

H

F, G

3