Question: Course: System Analysis and Design Code: IT 353 The following project activities have been defined with their required times for completion. Draw a network diagram
Course: System Analysis and Design
Code: IT 353
The following project activities have been defined with their required times for completion.
Draw a network diagram for the activities.
Calculate the early start time and early finish time.
Calculate the late start time and late finish time.
Show the critical path.
| Task ID | Task predecessors | Duration (days) |
| A | - | 3 |
| B | A | 4 |
| C | A | 2 |
| D | B | 5 |
| E | C | 1 |
| F | C | 2 |
| G | D, E | 4 |
| H | F, G | 3 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
