Question: The following project activities have been defined with their required times for completion. Task ID Task predecessors Duration (days) A - 3 B A 4
The following project activities have been defined with their required times for completion.
| Task ID | Task predecessors | Duration (days) |
| A | - | 3 |
| B | A | 4 |
| C | A | 2 |
| D | B | 5 |
| E | C | 1 |
| F | C | 2 |
| G | D, E | 4 |
| H | F, G | 3 |
a- Draw a network diagram for the activities.
b- Calculate the early start time and early finish time.
c- Calculate the late start time and late finish time.
d- Show the critical path.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
