Question: The following project activities have been defined with their required times for completion. Task ID Task predecessors Duration (days) A - 3 B A 4

The following project activities have been defined with their required times for completion.

Task ID

Task predecessors

Duration (days)

A

-

3

B

A

4

C

A

2

D

B

5

E

C

1

F

C

2

G

D, E

4

H

F, G

3

a- Draw a network diagram for the activities.

b- Calculate the early start time and early finish time.

c- Calculate the late start time and late finish time.

d- Show the critical path.