Question: Legend: Table: By using the Legend given below and information given in the Table, Early Start (ES) Late Start (LS) Activity Name A B
Legend: Table: By using the Legend given below and information given in the Table, Early Start (ES) Late Start (LS) Activity Name A B C D E F G H 1 J K Slack Activity Name Duration Planned Duration (days) 15 6 12 15 12 9 17 10 13 3 12 Early Finish (EF) Late Finish (LF) Dependence A - B, C A E D, E F G G, H J, I a) (15 pts) Construct the Activity on Node (AoN) network diagram b) (15 pts) By using the critical path method (CPM), compute the total project duration, and slack times for each activity. c) (5 pts) Identify the critical path. d) (5 pts) Now, assume that activity H has taken 5 days longer than its planned duration to complete. What happens to the ES, EF of other activities? e) (5 pts) Now, assume that activity H has taken 8 days longer than its planned duration to complete. What happens to the ES, EF of other activities?
Step by Step Solution
3.41 Rating (167 Votes )
There are 3 Steps involved in it
To solve the given problem lets address each part step by step a Construct the Activity on Node AoN Network Diagram To construct the AoN diagram we re... View full answer
Get step-by-step solutions from verified subject matter experts