Question: CPM Exercises CPM Exercise A Task Name Duration (days) Predecessor(s) Relationship A 2 B 6 C 4 A, B FS D 1 C FS E

CPM Exercises CPM Exercise A Task Name Duration (days) Predecessor(s) Relationship A 2 B 6 C 4 A, B FS D 1 C FS E 3 D SS F 1 B FS G 5 B FS H 1 F, G FS 2 E, H FS END 1. Develop a network diagram based on above table 2. What is the project duration of this network? CPM Exercise B Task Name Duration (Days) Predecessor(s) A 3 B 7 C 4 A(S-S) D 1 A, B E 6 D F 5 C,D G 2 E,F END G 1. Develop a network diagram based on above data 2. What is the Total Project duration