Question: Project Betelgeuse Task Task Description Duration Days Predecessor(s) Relationship A Task A 2 START FS B Task B 4 START FS+2 C Task C 2
- Project Betelgeuse
| Task | Task Description | Duration Days | Predecessor(s) | Relationship |
| A | Task A | 2 | START | FS |
| B | Task B | 4 | START | FS+2 |
| C | Task C | 2 | START | FS |
| D | Task D | 3 | A | FS+7 |
| E | Task E | 7 | B | FS |
| F | Task F | 8 | C | FS+5 |
| G | Task G | 2 | B, D | B(SF)+17, D(FS)+5 |
| H | Task H | 2 | E | FS+5 |
| I | Task I | 4 | F,G,H | FS |
| END | - | I | FS |
Hints: you will have to develop a network diagram and using Days 0 to perform CPM 1. The project duration is______days 2. The critical activity names between start and end are ____
. Each name is separated by a dash. 3. The ESD if activity H is day_____
4. The LSD if activity C is day____
5. The LFD if activity D is day_____ .
6. The management will allow for 25 days for the project to complete, the project float is______.
7. Will the project complete in 25 days? The answer is _______.
8. The EFD of activity G is day _________.