Question: Project Betelgeuse Task Task Description Duration Days Predecessor(s) Relationship A Task A 2 START FS B Task B 4 START FS+2 C Task C 2

  1. Project Betelgeuse

Task

Task Description

Duration Days

Predecessor(s)

Relationship

A

Task A

2

START

FS

B

Task B

4

START

FS+2

C

Task C

2

START

FS

D

Task D

3

A

FS+7

E

Task E

7

B

FS

F

Task F

8

C

FS+5

G

Task G

2

B, D

B(SF)+17, D(FS)+5

H

Task H

2

E

FS+5

I

Task I

4

F,G,H

FS

END

-

I

FS

Hints: you will have to develop a network diagram and using Days 0 to perform CPM 1. The project duration is______days 2. The critical activity names between start and end are ____

. Each name is separated by a dash. 3. The ESD if activity H is day_____

4. The LSD if activity C is day____

5. The LFD if activity D is day_____ .

6. The management will allow for 25 days for the project to complete, the project float is______.

7. Will the project complete in 25 days? The answer is _______.

8. The EFD of activity G is day _________.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!