Question: Crane Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm uses 11.50 percent
Crane Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm uses 11.50 percent to discount such project cash flows.
Year: 0,1,2,3,4
System 100: $1,856,700, 216,210, 478,230, 807,440, 754,300
System 200: $1,334,800, 568,400, 579,300, 484,700, 320,300
| NPV of system 100 is | $ | |
| NPV of system 200 is | $ |
Which system should be chosen?
| Crane should choose |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
