Question: crash costs. begin { tabular } { ccccc } hline Activity & begin { tabular } { c } Normal Time

crash costs.
\begin{tabular}{ccccc}
\hline Activity & \begin{tabular}{c}
Normal Time \\
(weeks)
\end{tabular} & \begin{tabular}{c}
Crash Time \\
(weeks)
\end{tabular} & \begin{tabular}{c}
Cost to Crash \\
(\$ per week)
\end{tabular} & Immediate Predecessor(s)\\
\hline A & 5 & 4 & 250 & None \\
B & 9 & 8 & 350 & None \\
C & 4 & 2 & 250 & A \\
D & 4 & 2 & 300 & A \\
E & 3 & 3 & - & B \\
F & 3 & 3 & - & C, D \\
G & 3 & 1 & 200 & D, E \\
H & 7 & 6 & 400 & F \\
I & 4 & 4 & - & G \\
\hline
\end{tabular}
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.)
\begin{tabular}{cc|cc}
\hline Activity & \begin{tabular}{l}
Time according to \\
schedule (weeks)
\end{tabular} & Activity & \begin{tabular}{l}
Time according to \\
schedule (weeks)
\end{tabular}\\
\hline A & 4 & F & 3\\
B & 8 & G & 1\\
C & 3 & H & 6\\
D & 3 & I & 4\\
E & 3 & & \\
\hline
\end{tabular}
The cost of shortening of project is \$ ..(Enter your response as a whole number.)
 crash costs. \begin{tabular}{ccccc} \hline Activity & \begin{tabular}{c} Normal Time \\ (weeks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!