Question: a) What would be your target completion week? b) How much would you save in total project costs with your schedule? addition, your project team
a) What would be your target completion week? b) How much would you save in total project costs with your schedule?
addition, your project team determined that indirect project costs are $1,500 per week. \begin{tabular}{cccccc} \hline Activity & Immediate Predecessor(s) & Normal Time (weeks) & Normal Cost ($) & Crash Time (weeks) & Crash Cost ($) \\ \hline A & & 2 & 3,000 & 1 & 8,000 \\ B & & 7 & 3,000 & 5 & 7,000 \\ C & A & 9 & 10,000 & 8 & 12,000 \\ D & A , B & 10 & 3,000 & 8 & 9,000 \\ E & B & 3 & 4,000 & 2 & 5,000 \\ F & D & 9 & 4,000 & 6 & 8,500 \\ G & E, F & 2 & 2,000 & 2 & 2,000 \\ H & G & 11 & 5,000 & 7 & 7,000 \\ I & C, F & 9 & 7,000 & 7 & 15,000 \\ \hline \end{tabular}