Question: crashing in order to decrease project time by 1 week, which activity should be crashed? crash cost / week = ( Crash cost - Normal

crashing
in order to decrease project time by 1 week, which activity should be crashed?
crash cost/week=(Crash cost- Normal cost)/(Normal Time-Crash Time)