Question: Create a critical path method for the slab cycle activities with the restrictions that there is no overtime. Monday to Friday, 8 hours a day.

Create a critical path method for the slab cycle activities with the restrictions that there is no overtime. Monday to Friday, 8 hours a day. Total project time length is 10 working business days. The below activity and duration is in no particular order. Please ensure that it makes sense.
Activity Duration
Start typical slab cycle 0 days
Button-up and pour wall & column gang forms 0.5 days
Clean and oil gang forms 0.5 days
Cure columns & walls 16 hours
Cure slab & landing 72 hours
Hoist flyforms (table forms - for building slab)0.5 days
Install duct work for kitchen & bath vents (in slab)0.5 days
Install electrical conduit in slab 0.25 days
Install slab bottom reinforcing steel 0.5 days
Install slab top reinforcement steel 0.5 days
Install temporary handrails & shore slab below 0.25 days
Install wall and column reinforcing & embedded conduit 0.25 days
Install plumbing and electrical cans (in slab)0.25 days
Layout & install one side of wall and column gang forms 0.25 days
Layout for slab inserts and embeds 0.25 days
Level flyforms and construct infills (for building slab)0.25 days
Mount electrical boxes onto gang forms (in columns & walls)0.25 days
Place and finish slab, and stair landing 1 day
Strip columns and walls (gang forms)0.25 days
End of typical slab 0 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!