Question: create a gant chart ( visual ) based on the following: Activity Description Time ( hrs ) Immediate Predecessor ( s ) I Put grass
create a gant chart visual based on the following: Activity Description Time hrs Immediate Predecessors
I Put grass all over the garden, landscape, paint
H Put dirt around the equipment F
G Put sand in and under the equipment F
F Nail lumber together E
E Position lumber in correct locations D C
D Saw lumber into appropriate sizes B
C Dig and grade A
B Requisition of lumber and sand A
A Find location determine resource requirements