Question: create a gant chart ( visual ) based on the following: Activity Description Time ( hrs ) Immediate Predecessor ( s ) I Put grass

create a gant chart (visual) based on the following: Activity Description Time (hrs) Immediate Predecessor(s)
I Put grass all over the garden, landscape, paint 25
H Put dirt around the equipment 15 F
G Put sand in and under the equipment 15 F
F Nail lumber together 5 E
E Position lumber in correct locations 25 D, C
D Saw lumber into appropriate sizes 30 B
C Dig and grade 100 A
B Requisition of lumber and sand 60 A
A Find location determine resource requirements 15-