Question: Activity Description Time (hrs) Immediate Predecessor(s) A Find location determine resource requirements 25 - B Requisition of lumber and sand 55 A C Dig and

Activity Description Time (hrs) Immediate Predecessor(s) A Find location determine resource requirements 25 - B Requisition of lumber and sand 55 A C Dig and grade 95 A D Saw lumber into appropriate sizes 35 B E Position lumber in correct locations 25 D, C F Nail lumber together 15 E G Put sand in and under the equipment 20 F H Put dirt around the equipment 10 F I Put grass all over the garden, landscape, paint 25 G, H Using the line drawing tool, draw a Gantt chart for activities E through I of the project