Question: Create a load profile table (0-3) for the following widget: An end-item widget is assembled from 4 subassemblies of type A36, 2 B11s and 1
Create a load profile table (0-3) for the following widget: An end-item widget is assembled from 4 subassemblies of type A36, 2 B11s and 1 C3S. Bach A36 is made from a B22 and 2 B19s. Each B22 is made using a C7 and a purchased part number D19. All A type parts are made in the A department, B type parts are made in the B department, and C type parts are made in the C department. Lead times are all one week. Bach A36 requires 0.5 hours of department time. Each B22 requires 2.5 hours of department time. The other part types all take one hour of department resource per unit. Develop a load profile for a widget.