Question: Create a minimum cost chase plan for the forecast shown in the table. There is no beginning inventory and regular production capacity is 350 units.
Create a minimum cost chase plan for the forecast shown in the table. There is no beginning inventory and regular production capacity is 350 units. Overtime costs $20 and is limited to 50 units per month and subcontracting is limited to 100 units per month and costs $15 per unit. What is the total plan cost (i.e. subcontracting + overtime)?
Hint: In a chase production plan, production is changed each time period to match the demand. Use regular production, overtime, and subcontracting to create the plan.
| Month | Forecast | Regular | Overtime | Subcontracting |
| January | 250 |
|
|
|
| February | 400 |
|
|
|
| March | 500 |
|
|
|
| April | 350 |
|
|
|
3) A firm wishes to assign a set of jobs to a set of machines. The table below provides data on the cost of production of each job when performed on a specific machine.
a) Determine the set of assignments that minimizes production cost.
b) What is the total production cost of your assignments?
|
| Machine | |||
| Job | A | B | C | D |
| 1 | 27 | 29 | 28 | 30 |
| 2 | 30 | 29 | 27 | 26 |
| 3 | 31 | 25 | 29 | 26 |
| 4 | 29 | 31 | 25 | 28 |
4) Using the information given in the table, find the sequence for the following priority rules:
a) SPT
b) EDD
c) LPT
| Job | Process Time | Due Date |
| A | 6 | 10 |
| B | 4 | 2 |
| C | 8 | 5 |
| D | 9 | 16 |