Question: 3) Create a minimum cost chase plan for the forecast shown in the table. There is no beginning inventory and regular production capacity is 350
3) Create a minimum cost chase plan for the forecast shown in the table. There is no beginning inventory and regular production capacity is 350 units and costs $8 per unit. Overtime costs $19 and is limited to 50 units per month and subcontracting is limited to 100 units per month and costs $14 per unit. What is the total plan cost?
Hint: In a chase production plan, production is changed each time period to match the demand. Use regular production, overtime, and subcontracting to create the plan.
| Month | Forecast | Regular | Overtime | Subcontracting |
| January | 250 |
|
|
|
| February | 400 |
|
|
|
| March | 500 |
|
|
|
| April | 350 |
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts