Question: Create a network diagram using a forward pass and reverse pass from the following table: Activity Preceding Activity Duration in Weeks Start None 0 A

Create a network diagram using a forward pass and reverse pass from the following table: Activity Preceding Activity Duration in Weeks Start None 0 A Start 1 B A 2 C Start 6 D A 10 E B,C 1 F C 2 G E 3 H G 9 I F 1 End D,H,I 0 Adapted from RMC 10th Edition Pass PMP Guide Value: 10 The earliest the project can finish is 19 weeks . The earliest activity I can finish is 0 weeks . The amount of float on task F is 0 weeks