Question: Create a new dependency in the project, from the baseline project in Q 1 , such that activity C now can only start when B

Create a new dependency in the project, from the baseline project in Q1, such that activity C now can only start when B and D are completed. Re-calculate and state the new critical path and the new completion time if they change, and location and length of the new slack times by pathway.