Question: create a PERT Chart for the following activities: CAN BE HAND DRAWN Activity Duration Predecessor A 2 - B 4 - C 6 A,B D

create a PERT Chart for the following activities: CAN BE HAND DRAWN

Activity Duration Predecessor

A 2 -

B 4 -

C 6 A,B

D 1 A,B

E 2 B,C,D