Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A B A A B C D D 4 3 5 6 7 2

Schedule the following activities using CPM:

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A B A A B C D D 4 3 5 6 7 2 3 4 G EG b. What is the critical path? A-B-D-F-G-H A-B-D-G-H A-B-D-E-H O A-C-D-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OB. 3 weeksi H. 2 weeks ;F. 1 week. OC. 4 weeks ;F. 2 weeks : G. 2 weeks. B. 1 week: C. 3 weeks : F. 2 weeks