Question: Create a PERT Chart from the following information -Identify your Predecessors -Identify your CPM (Critical Path) -Identify your ES/EF, LS/LF and Slack Times -Upload on

Create a PERT Chart from the following information -Identify your Predecessors -Identify your CPM (Critical Path) -Identify your ES/EF, LS/LF and Slack Times -Upload on the Canvas Assignment Page by Sunday July 16 Task Description Duration (Days) Predecessor T1 Systems Analysis 5 T2 Analysis Report 15 T1 T3 Systems Design 25 T2 T4 Devising Algorithms 15 T2 T5 Coding 30 T2 T6 Testing 10 T3,T4 T7 Implementation 10 T5,T6 T8 Review 5 T7 T9 Evaluate Hardware 5 T8