Question: Create a PERT chart given the data below Task Code Immediately Preceding Task Estimated Duration (days) T01 - 7 T02 - 7 T03 - 7
Create a PERT chart given the data below
| Task Code | Immediately Preceding Task | Estimated Duration (days) |
| T01 | - | 7 |
| T02 | - | 7 |
| T03 | - | 7 |
| T04 | T01, T02, T03 | 10 |
| T05 | T04 | 6 |
| T06 | T05 | 1 |
| T07 | T06 | 1 |
| T08 | T07 | 1 |
| T09 | - | 7 |
| T10 | T09 | 1 |
| T11 | - | 7 |
| T12 | T10, T11 | 1 |
| T13 | T08 | 1 |
| T14 | T12, T13 | 1 |
| T15 | T14 | 1 |
| T16 | T15 | 2 |
| T17 | T16 | 21 |
| T18 | T17 | 1 |
| T19 | T18 | 1 |
| T20 | T19 | 1 |
| T21 | T20 | 1 |