Question: Create a PERT chart given the data below Task Code Immediately Preceding Task Estimated Duration (days) T01 - 7 T02 - 7 T03 - 7

Create a PERT chart given the data below

Task Code Immediately Preceding Task Estimated Duration (days)
T01 - 7
T02 - 7
T03 - 7
T04 T01, T02, T03 10
T05 T04 6
T06 T05 1
T07 T06 1
T08 T07 1
T09 - 7
T10 T09 1
T11 - 7
T12 T10, T11 1
T13 T08 1
T14 T12, T13 1
T15 T14 1
T16 T15 2
T17 T16 21
T18 T17 1
T19 T18 1
T20 T19 1
T21 T20 1