Question: Create a project network from the information below. Do both a forward pass and a backward pass, and identify the float of each activity. Activity
Create a project network from the information below. Do both a forward pass and a backward pass, and identify the float of each activity.
Activity Duration(Days) Predecessors
A 1 -
B 2 A
C 3 A
D 4 A
E 5 B
F 4 B
G 6 C
H 6 D, G
I 2 E
J 2 F, H, I
What is the critical path?
Which activities would be good candidates for crashing? Why?
Which activities would be good candidates for fast tracking? Why?