Question: Create a RBS from this WBS: WBS Task Mode Task Name Fixed Cost Cost Duration Start Finish Predecessors Successors Resource Names 1 Auto Scheduled CFEH

Create a RBS from this WBS:

WBS Task Mode Task Name Fixed Cost Cost Duration Start Finish Predecessors Successors Resource Names
1 Auto Scheduled CFEH Online Pharmacy Project $0.00 $485,803.80 408 days? Wed 7/21/21 Fri 2/10/23
1.1 Auto Scheduled Initiating $0.00 $58,953.85 45 days? Wed 7/21/21 Tue 9/21/21
1.1.1 Auto Scheduled Develop CFEH Project Scope and Plan $0.00 $13,615.38 10 days Wed 7/21/21 Tue 8/3/21 4 Lauren PM,CFEH Project Team: Chris,CFEH Project Team: Susan,CFEH Partners ,Jose VPO
1.1.2 Auto Scheduled Develop a CFEH Project Charter $0.00 $24,661.54 14 days Wed 8/4/21 Mon 8/23/21 3 5 CFEH Partners ,Confrenece Room Rental,Jose VPO,Lauren PM,Projector rental
1.1.3 Auto Scheduled Engage Stakeholders: CFEH Partners $0.00 $13,946.15 7 days? Tue 8/24/21 Wed 9/1/21 4 6 CFEH Partners ,Confrenece Room Rental,Dinner for 10 people,Jose VPO,Lauren PM,Projector rental,CFEH Project Team: Chris
1.1.4 Auto Scheduled Signatures of approval on Contract $0.00 $6,730.77 7 days Mon 9/13/21 Tue 9/21/21 5 8 CFEH Partners ,Lauren PM,Jose VPO
1.2 Auto Scheduled Planning $0.00 $87,321.85 132 days Wed 9/22/21 Thu 3/24/22
1.2.1 Auto Scheduled Portal Design $0.00 $18,692.31 45 days Wed 9/22/21 Tue 11/23/21 6 9 CFEH Partners ,Lauren PM,MidWest Tech Team,Online Portal Subscription
1.2.2 Auto Scheduled Project Scope Plan $0.00 $39,711.54 50 days Wed 11/24/21 Tue 2/1/22 8 10,28 Lauren PM,MidWest Tech Team,CFEH Project Team: Chris,CFEH Project Team: Susan
1.2.3 Auto Scheduled Risk Management Plan $0.00 $11,769.23 15 days Wed 2/2/22 Tue 2/22/22 9 11 CFEH Project Team: Chris,Lauren PM,CFEH Project Team: Susan
1.2.4 Auto Scheduled Budget/ Cost Estimates $0.00 $5,559.62 7 days Wed 2/23/22 Thu 3/3/22 10 12 CFEH Project Team: Chris,Lauren PM,MidWest Tech Team,CFEH Project Team: Susan
1.2.5 Auto Scheduled Generate a Project Organization Chart $0.00 $2,800.00 7 days Fri 3/4/22 Mon 3/14/22 11 13 CFEH Project Team: Chris,CFEH Project Team: Susan
1.2.6 Auto Scheduled Create a Work Breakdown Structure $0.00 $5,492.31 7 days Tue 3/15/22 Wed 3/23/22 12 14 Lauren PM,CFEH Project Team: Chris,CFEH Project Team: Susan
1.2.7 Auto Scheduled Project Kickoff Meeting $0.00 $3,296.85 1 day Thu 3/24/22 Thu 3/24/22 13 16 CFEH Project Team: Chris,Confrenece Room Rental,Jose VPO,Lauren PM,Marketing Team: Katie G,MidWest Tech Team,Projector rental,Travel Expense,Triple Crown Software,CFEH Project Team: Susan,Jake- CFEH IT Assistant,Pharmacy Staff: Celeste,Pharmacy Staff: S...
1.3 Auto Scheduled Execution $0.00 $158,855.10 77.5 days Fri 3/25/22 Tue 7/12/22
1.3.1 Auto Scheduled Online Portal Design $50,000.00 $83,738.46 15 days Fri 3/25/22 Thu 4/14/22 14 17 CFEH Project Team: Chris,Jose VPO,Lauren PM,Marketing Team: Katie G,MidWest Tech Team,MidWest Vet Supply Technical Support,Online Portal Subscription ,CFEH Project Team: Susan,Travel Expense,CFEH Partners ,Confrenece Room Rental,Jake- CFEH IT Assistant,...
1.3.2 Auto Scheduled Piloting and Delivering $0.00 $28,557.69 30 days Fri 4/15/22 Thu 5/26/22 16 18 MidWest Tech Team,MidWest Vet Supply Technical Support,Jake- CFEH IT Assistant,Lauren PM,Stephen- CFEH IT Manager
1.3.3 Auto Scheduled Development of Application $25,000.00 $26,698.72 3.33 days Fri 5/27/22 Wed 6/1/22 17 19 Stephen- CFEH IT Manager ,Jake- CFEH IT Assistant,MidWest Tech Team
1.3.4 Auto Scheduled Interface with MidWest Vet Supply operation $0.00 $3,562.15 2 days Wed 6/1/22 Fri 6/3/22 18 20 CFEH Project Team: Chris,Jake- CFEH IT Assistant,MidWest Tech Team,Stephen- CFEH IT Manager ,CFEH Project Team: Susan,Lauren PM,MidWest Vet Supply Technical Support,MW Pharmacy Technician ,Online Portal Subscription ,Pharmacy Staff: Celeste,Pharmacy Sta...
1.3.5 Auto Scheduled Interface Communications $0.00 $2,548.08 5 days Fri 6/3/22 Fri 6/10/22 19 21 Jake- CFEH IT Assistant,MidWest Tech Team,Stephen- CFEH IT Manager
1.3.6 Auto Scheduled Information Security Management $0.00 $3,500.00 7 days Mon 6/13/22 Tue 6/21/22 20 22 Jake- CFEH IT Assistant,Stephen- CFEH IT Manager
1.3.7 Auto Scheduled Platform Demo/ Internal User Allocation $0.00 $9,778.85 7.5 days Wed 6/22/22 Fri 7/1/22 21 23,28 CFEH Project Team: Chris,Jake- CFEH IT Assistant,Lauren PM,Stephen- CFEH IT Manager ,CFEH Partners ,CFEH Veterinarians,Confrenece Room Rental,Travel Expense,CFEH Project Team: Susan
1.3.8 Auto Scheduled Platform Maintenance/ Repair $0.00 $471.15 7 days Fri 7/1/22 Tue 7/12/22 22 25 MidWest Tech Team,MidWest Vet Supply Technical Support
1.4 Auto Scheduled Live Enviroment $0.00 $45,925.23 12 days Tue 7/12/22 Thu 7/28/22
1.4.1 Auto Scheduled Platform Launch to Clientele $10,000.00 $26,651.54 5 days Tue 7/12/22 Tue 7/19/22 23 26,28 CFEH Project Team: Chris,Jake- CFEH IT Assistant,Jose VPO,Lauren PM,Marketing Team: Katie G,MidWest Tech Team,Online Portal Subscription ,Stephen- CFEH IT Manager ,Triple Crown Software,CFEH Project Team: Susan,MidWest Vet Supply Technical Support,MW Ph...
1.4.2 Auto Scheduled Perscription intake and first orders shipped $0.00 $19,273.69 7 days Tue 7/19/22 Thu 7/28/22 25 28 CFEH Project Team: Chris,Jake- CFEH IT Assistant,Lauren PM,Marketing Team: Katie G,MidWest Tech Team,MidWest Vet Supply Technical Support,MW Pharmacy Technician ,Online Portal Subscription ,Pharmacist,Pharmacy Staff: Sherena,Stephen- CFEH IT Manager ,Tr...
1.5 Auto Scheduled Management and Control $0.00 $104,886.24 60 days Thu 7/28/22 Thu 10/20/22
1.5.1 Auto Scheduled Regular Team meetings $0.00 $2,084.62 1 day Thu 7/28/22 Fri 7/29/22 22,25,9,26 29 CFEH Project Team: Chris,Jake- CFEH IT Assistant,Lauren PM,Stephen- CFEH IT Manager ,CFEH Project Team: Susan,Projector rental
1.5.2 Auto Scheduled Portal Testing $0.00 $11,974.31 14 days Fri 7/29/22 Thu 8/18/22 28 30 Jake- CFEH IT Assistant,MidWest Tech Team,Stephen- CFEH IT Manager ,MidWest Vet Supply Technical Support,Pharmacy Staff: Celeste,Pharmacy Staff: Sherena
1.5.3 Auto Scheduled Quality Control and Clientele and Vet Training $0.00 $38,029.62 15 days Thu 8/18/22 Thu 9/8/22 29 31 CFEH Project Team: Chris,Jake- CFEH IT Assistant,Lauren PM,MidWest Tech Team,MidWest Vet Supply Technical Support,Stephen- CFEH IT Manager ,CFEH Project Team: Susan,Jose VPO,Marketing Team: Katie G,Pharmacy Staff: Celeste,Pharmacy Staff: Sherena,Triple ...
1.5.4 Auto Scheduled Monitor the Changes $0.00 $52,797.69 30 days Thu 9/8/22 Thu 10/20/22 30 33 CFEH Project Team: Chris,Jake- CFEH IT Assistant,Lauren PM,Stephen- CFEH IT Manager ,CFEH Project Team: Susan,MidWest Tech Team,MidWest Vet Supply Technical Support,MW Pharmacy Technician ,Pharmacy Staff: Celeste,Pharmacy Staff: Sherena
1.6 Auto Scheduled CloseOut $0.00 $29,861.54 81.5 days Thu 10/20/22 Fri 2/10/23
1.6.1 Auto Scheduled Audit Performance $0.00 $13,307.69 25 days Thu 10/20/22 Thu 11/24/22 31 34 CFEH Project Team: Chris[20%],Jake- CFEH IT Assistant[20%],Jose VPO[20%],Lauren PM[20%],Stephen- CFEH IT Manager [20%],CFEH Project Team: Susan
1.6.2 Auto Scheduled Close out reports/ Lessons Learned $0.00 $4,000.00 10 days Thu 1/5/23 Wed 1/18/23 33 35 CFEH Project Team: Chris,Lauren PM,CFEH Project Team: Susan
1.6.3 Auto Scheduled Documenting the Projects Files for future reference $0.00 $12,553.85 16 days Fri 1/20/23 Fri 2/10/23 34 CFEH Project Team: Chris,Lauren PM,CFEH Project Team: Susan,CFEH Veterinarians

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!