Question: Create a visual task of the below project Phase / Task Estimated Duration Milestone Contractor Effort Start Date End Date 1 . Project Planning &

Create a visual task of the below project Phase/Task Estimated Duration Milestone Contractor Effort Start Date End Date1. Project Planning & Design3 weeks Initial Design Approval Medium March 1,2025 March 21,20251.1. Initial Consultation1 week Design Requirements Low March 1,2025 March 7,20251.2. Design Draft & Approval2 weeks Final Design Medium March 8,2025 March 21,20252. Demolition1 week Cleared Space High March 22,2025 March 28,20253. Structural Modifications2 weeks Inspection Passed High March 29,2025 April 11,20254. Electrical & Plumbing3 weeks Inspection Passed Medium April 12,2025 May 2,20255. Flooring & Cabinetry4 weeks Cabinet Installation Medium May 3,2025 May 30,20256. Appliances & Finishing2 weeks Final Walkthrough Medium June 1,2025 June 14,20257. Final Inspection & Handover2 weeks Project Completion Low June 15,2025 June 30,2025

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!