Question: Create an activity - on - node schedule for the following activities. Each node should be complete with early start, late start, early finish, late

Create an activity-on-node schedule for the following activities. Each node should be complete with early start, late start, early finish, late finish, and float. The critical path should be highlighted.
\table[[Activity,Duration,Predecessor,Successor],[A,1,None,B,],[B,4,A,D],[C,5,A,D],[D,2,B, C,E],[E,3,D,F, G, H],[F,9,E,I],[G,4,E,I],[H,6,E,I],[I,2,F, G, H,J],[J,1,I,None]]