Question: Create and complete a MRP planning schedule using the following assumptions: We do not have any finished products available. Our demand is 15 double vanities
Create and complete a MRP planning schedule using the following assumptions: We do not have any finished products available. Our demand is 15 double vanities with sinks on days 5, 8 and 10. Note: You do not have to create a MRP grid for all materials (only the materials listed in the excel workbook) CELL REFERENCING is required for Gross Requirements of each item (only) Item Lead Time (Day) Safety Stock POH Schedule Receipts Lot Size Countertop 2 0 0 0 L4L Vessel Sinks 1 0 5 0 FOQ 5 Vanity Box 1 0 0 30 on day 1 1 Legs 1 0 0 0 1 French Cleats 1 0 10 0 1 Face 1 20 20 0 FOQ 25 Drawers 1 0 0 0 FOQ 20 Doors 2 25 25 0 FOQ 50
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts