Question: Create and complete an MRP planning schedule using the following assumptions: We do not have any finished products available. Our demand is 225 cakes on
Create and complete an MRP planning schedule using the following assumptions:
We do not have any finished products available.
Our demand is 225 cakes on wk 4 and 200 cakes on wk 8.
We do not have anything in inventory except for what is noted below
Remember: The final product for the customer is made up of one cake, 1 custard filling and 2 icings
| Item | Lead Time (Day) | Safety Stock | POH | Schedule Receipts | Lot Size |
| Vanilla Bean Cake | 1 | 0 | 0 | 0 | L4L |
| Final Product | 1 | 0 | 0 | 0 | LFL |
| Flour | 1 | 0 | 1000 | 100 On day 1 | 100 |
| Vanilla Bean Paste | 1 | 0 | 0 | 0 | 100 |
| Thickened Cream | 1 | 250 | 250 | 10,000 On day 2 | FOQ 1,000 |
| Custard Filing | 1 | 0 | 0 | 0 | LFL |
| Icing | 1 | 0 | 0 | 0 | LFL |
| Eggs | 1 | 0 | 1000 | 0 | LFL |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts