Question: Create and complete an MRP planning schedule using the following assumptions: We do not have any finished products available. Our demand is 225 cakes on

Create and complete an MRP planning schedule using the following assumptions:

We do not have any finished products available.

Our demand is 225 cakes on wk 4 and 200 cakes on wk 8.

We do not have anything in inventory except for what is noted below

Remember: The final product for the customer is made up of one cake, 1 custard filling and 2 icings

Item

Lead Time

(Day)

Safety

Stock

POH

Schedule

Receipts

Lot Size

Vanilla Bean Cake

1

0

0

0

L4L

Final Product

1

0

0

0

LFL

Flour

1

0

1000

100 On day 1

100

Vanilla Bean Paste

1

0

0

0

100

Thickened Cream

1

250

250

10,000 On day 2

FOQ 1,000

Custard Filing

1

0

0

0

LFL

Icing

1

0

0

0

LFL

Eggs

1

0

1000

0

LFL

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!