Question: Create new Project in MS Project: Prepare Tea Party 1 . 1 Send invitation - 2 days 1 . 2 Combine attendance confirmation - 1

Create new Project in MS Project:
Prepare Tea Party
1.1 Send invitation -2 days
1.2 Combine attendance confirmation -1 day
1.3 Create menu -1 day
1.4 Buy the products 1 day
1.5 Cook deserts -2 days -10 hours
1.6 Run Party -6 hours -0.25 of day (be creative, you need hours to adjust the servant's hours)
1.7 Clean -1 day.
Resources:
Manager -$30/h
Cook - $20/h
Servant -16/h,6 hours
Cleaner 16/h,5 hours
Food - $50 per invited person, plan to host 20 people
Rent room - one time payment before the party.