Question: Create project P6 Assignment 4, start date 5/1/2020 Add all the activities in the picture below and arrange the sequences accordingly. All activities should be

Create project "P6 Assignment 4", start date "5/1/2020" Add all the activities in the picture below and arrange the sequences accordingly. All activities should be "task dependent" and the duration type should be "Fixed Duration & Units" Submit the following screenshots and answers: a. Activity table b. Activity Network C. From left to right, explain the relationships in each circle. For example, for the first circle: "web theme design" and "process diagram level one" can be conducted at the same time but only after "improved use-case diagram" is finished. Note: Although each activity on the picture has dates, do not worry about the dates for now. We are only focusing on the sequences for this assignment
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
