Question: Create the Earliest Start Earliest Finish chart for the following and answer the questions. Immediate Activity Predecessor Time A - 2 B - 3 C

Create the Earliest Start Earliest Finish chart for the following and answer the questions.
Immediate
Activity Predecessor Time
A -2
B -3
C -4
D A,B 3
E B,C 5
F D,E 1
G E 2
a) What is the Latest Finish (LF) for activity G?
b) Which Activities have Slack?
c) What is the Critical Path?