Question: The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project. TaskPreceding Tasks A.. None B.. A

The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project.
Task…………Preceding Tasks
A………….. None
B………….. A
C………….. A
D………….. B
E………….. C
F………….. D, E