Question: Critical Path Analysis Given the following information, create an AON critical path. You may use the Chpt . 8 - Project Management PowerPoint presentation as
Critical Path Analysis
Given the following information, create an AON critical path. You may use the ChptProject Management PowerPoint presentation as a guide on how to construct the path analysis. Hint: your first Activity on Node AON should be start as illustrated on slide and slides will guide you on how to correctly create the analysis.
Activity Immediate Predecessors Duration
A
B
C A
D AB
E C
F C
G DE
H FG