Question: Critical Path Analysis Given the following information, create an AON critical path. Additional information may be found in Chpt. 8 and Module 8 as a

Critical Path Analysis

Given the following information, create an AON critical path. Additional information may be found in Chpt. 8 and Module 8 as a guide on how to construct the path analysis. Hint: your first AON should be start as illustrated on slide 84 and slides 74-84 will greatly benefit you from the Project Management Chapter 8 PowerPoint presentation.

Activity

Immediate Predecessors

Duration

A

10

B

15

C

AB

21

D

C

29

E

C

35

F

E

48

G

DF

50