Question: Critical Path for Pixar. The following table lists the activity times (in months) for the project network describing the production of an animated movie at

Critical Path for Pixar. The following table lists the activity times (in months) for the project network describing the production of an animated movie at Pixar Studios in Problem 3. a. Find the critical path. b. The project must be completed in 1.5 years. Do you anticipate difficulty in meeting the deadline? Explain.

ActivityABCDEFGTime4626335