Question: Critical Path Method Homework | Activity | Duration (weeks) | Predecessor(s) | A 12 None B 3 None C 8 A D 5 C E
Critical Path Method Homework | Activity | Duration (weeks) | Predecessor(s) |
A 12 None
B 3 None
C 8 A
D 5 C
E 18 D
F 6 B, E
G 5 F
H 2 B
I 5 H
Draw a project network and find the critical path and the minimum number of days needed to finish the work.
Also find out the earliest start and finish time for each activity.