Question: Critical Path Method||Project Management Technique Operations Research / 1. Consider a project with activities A, B, C, D, E and F. The following table shows

Critical Path Method||Project Management

Critical Path Method||Project Management Technique Operations Research / 1. Consider a project with activities A, B, C, D, E and F. The following table shows the precedence and duration (in days) of each one of the activities. Activity Predecessors Duration (days) 10 A,F A,B,E 10 12 F 7 B 15 E 8 D E A a) Draw the project network (Including the dummy activity) b) Indicate the project duration (Include the forward and backward pass). What is the critical path ? Justify your