Question: Critical Path Method|Project Management Technique||Operations Research / 1. Consider a project with activities A, B, C, D, E and F. The following table shows the

Critical Path Method|Project Management

Critical Path Method|Project Management Technique||Operations Research / 1. Consider a project with activities A, B, C, D, E and F. The following table shows the precedence and duration (in days) of each one of the activities. Activity Predecessors Duration (days) 10 A B 15 C 8 A,F E A,B,E A D E F 10 12 7 a) Draw the project network diagram b) Indicate the duration of the project. What is the critical path? Justify