Question: critical path of the project? table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,DURATION ( days ) ] , [ A , - , 1 ]

critical path of the project?
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,DURATION (days)],[A,-,1],[B,A,4],[C,A,3],[D,A,7],[E,B,6],[F,C,D,2],[G,E,F,7],[H,D,9],[I,G,H,4]]
ACEGI
ACFGI
ADHI
ADFGI
ABEGI
 critical path of the project? \table[[ACTIVITY,IMMEDIATE PREDECESSOR,DURATION (days)],[A,-,1],[B,A,4],[C,A,3],[D,A,7],[E,B,6],[F,C,D,2],[G,E,F,7],[H,D,9],[I,G,H,4]] ACEGI ACFGI ADHI