Question: Critical Path Problem (14 points): Below is the information needed to complete this project management problem. Time (weeks) Slack 12 Activity Immediate Predecessor A --

Critical Path Problem (14 points): Below is the

Critical Path Problem (14 points): Below is the information needed to complete this project management problem. Time (weeks) Slack 12 Activity Immediate Predecessor A -- B -- C -- D A E A FB G D HE.E 11 13 10 9 7 8 4 7 Draw the flowchart for this problem. Identify the critical path and calculate the slack for each of the activities. You can put your slack times in the table. Show your work