Question: Critical path Time, resource and relationships for a project: Which activity or activities are on the critical path? (More than one is correct). A B

Critical path

Time, resource and relationships for a project:

Critical path Time, resource and relationships for a project: Which activity or

Which activity or activities are on the critical path?

(More than one is correct).

A

B

C

D

E

\begin{tabular}{|c|c|c|c|} \hline Activity & Predecessor & Duration & Resources \\ \hline A & None & 2 & 3 \\ \hline B & A & 1 & 2 \\ \hline C & A & 5 & 1 \\ \hline D & B and C & 3 & 3 \\ \hline E & D & 4 & 1 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!