Question: critical path tracking template , i need to know what are the critical tasks and the flixable tasks DRAG-Delay Calculation TASK TASKG 37 10 TASK
critical path tracking template , i need to know what are the critical tasks and the flixable tasks
DRAG-Delay Calculation TASK TASKG 37 10 TASK TASKA TASKH DRAG=10 DRAGIS DRAGS DRAG=5 DRAG-20 O 17.6 17. 3 4,33 9.33 9.33 8.33 TASKC TASKD TASKE PROJECT DESCRIPTION AND TIME ESTIMATES (WEEKS) Cask Description Most optimistic Most likely IP eco A B D E F G H 1 J K Requirements Market assessment Design Development Testing Revising Documentation Quality assurance Pricing Production Distribution NWNNWANAN 3 7 6 7 9 5 6 4 2 4 3 or Most pessimistic 4 10 9 16 10 6 10 7 2 14 4 D BE D CE B F,G,H,1 J Created by authors