Question: cted View Enable Editing Use the information provide below to answer the questions that follows:- Activity Duration Predecessor A 16 B 8 A 6 D

cted View Enable Editing Use the information provide below to answer the questions that follows:- Activity Duration Predecessor A 16 B 8 A 6 D 14 E 2 B F 4 G DEF 1. During which project knowledge area is the information above useful to the project? 2 Marks 2. In which phase of the project does the information above apply? 2 Marks 3. Use the information provided to draw an AON diagram 9 Marks 4 Show all the paths of the network diagram above 6 Marks 5 Indicate the critical path of the project. 1 Marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock