Question: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 21 33 57 B 1


TIMES (days)

Activity

Start Node

Finish Node

OPTIMISTIC

to

MOST LIKELY

tm

PESSIMISTIC

tp

A

1

2

21

33

57

B

1

3

24

30

48

C

2

5

14

26

62

D

3

4

32

38

56

E

4

5

15

36

57


Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values:


Activity A………te = 30
Standard Deviation = 3


Activity B………te =

Standard Deviation =

Activity C………te =

Standard Deviation =


Activity D………te =

Standard Deviation =

Activity E………te =

Standard Deviation = 4


Path 1 – 2 – 5
Mean Time =

Standard Deviation =5


Path 1 – 3 – 4 – 5
Mean Time =

Standard Deviation =

Step by Step Solution

3.50 Rating (153 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

tattutte to ta Cinish Node ton te Activity SD e stast ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

635dd4b10df36_179227.pdf

180 KBs PDF File

Word file Icon

635dd4b10df36_179227.docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!