Question: Current Attempt in Progress Amos, Inc. uses a standard cost system with the following labor standards for one unit of product standard hours 0.1 and

 Current Attempt in Progress Amos, Inc. uses a standard cost system

Current Attempt in Progress Amos, Inc. uses a standard cost system with the following labor standards for one unit of product standard hours 0.1 and standard waterate $10 During January, Amos incurred 1.855 hours of direct labor and paid $18,039 in wages in production of 17 500 units Calculate the direct labor rate and efficiency variances and indicate whether the variances we favorable or untivorable Direct laborate variance $ Direct labor efficiency variance $ Attempts of used Sun