Question: Current Attempt in Progress During 2022, Sunland Manufacturing expected Job No. 59 to incur $360000 of overhead cost, $560000 of direct materials cost, and
Current Attempt in Progress During 2022, Sunland Manufacturing expected Job No. 59 to incur $360000 of overhead cost, $560000 of direct materials cost, and $100000 in direct labor cost. Sunland applied overhead based on direct labor cost. Actual production required overhead cost of $290000, $580000 in direct materials used, and $200000 in direct labor. All of the goods were completed. What is the amount of over- or underapplied overhead?
Step by Step Solution
3.47 Rating (160 Votes )
There are 3 Steps involved in it
To calculate the over or underapplied overhead we can use the following formula Ov... View full answer